FT.com
September
18, 2013 8:13pm
By
Henry Mance
There are several ways the US Air Force
could have wasted $1.1bn. It could have poured tomato ketchup into 250m gallons
of jet fuel or bought a sizeable stake in Bear Stearns.
Instead it upgraded its IT systems.
Work began in 2007 to reconfigure how the force managed its logistics, with the
aim of replacing 200 dated networks with a single piece of Oracle software. By
the time the project was abandoned last November, it was at least four years
behind schedule and would have required an additional $1.1bn to become usable.
Yet in making such mistakes, the Air
Force is not flying solo.
This week a UK parliamentary
watchdog described a failed National Health
Service patient IT programme – the cost of which has spiralled to £9.8bn – as
“one of the worst and most expensive contracting fiascos in the history of the
public sector”. Earlier this month the Department for Work and Pensions
admitted that it had written off £34m of IT costs, incurred in an attempt to
overhaul how social security benefits are paid. A week earlier Co-operative
Bank said it had written off the £148m cost of a new IT system that would no
longer be implemented.
“It is quite scary,” says Ralf
Dreischmeier, the global head of Boston Consulting Group’s IT practice. “From
my experience, 20 per cent of projects fail, and 40-50 per cent have a cost
overrun, time overrun or don’t meet requirements. Only a third could be
described as good projects.”
Why are companies and governments still
suffering such embarrassing failures?
In a
2011 study, Bent Flyvbjerg and Alexander
Budzier at Oxford university’s Saïd Business School examined 1,471 IT projects
against their forecast costs and overruns. They found that the projects
exceeded their budgets by an average of one-quarter.
“Over the past decade there have been
no improvements even though a lot of things have been tried,” says Mr Budzier.
The researchers posited that planners consistently underestimated the costs and
overestimated the benefits of IT projects. They also failed to appreciate the
“black swan” scenario – that is, the chance that something will go really
wrong.
Citing Nicholas Nassim Taleb, author of
the book The Black Swan, the researchers argue that “the high
over-incidence of black swans underlines that ICT projects are a very important
source of uncertainty in an organisation”. In one in six projects examined by
Prof Flyvbjerg and Mr Budzier, the cost was at least triple what had been
estimated. When Hershey’s, the chocolate maker, implemented a new ordering
system, it ended up missing out on a whole Halloween of sweet sales, worth
$100m.
What have we learnt from
past mistakes?
Make realistic estimates
“People always underestimate the cost of software development. Suppliers always push their prices,” says John Fotheringham, a partner at Deloitte.
“People always underestimate the cost of software development. Suppliers always push their prices,” says John Fotheringham, a partner at Deloitte.
Keep it short
Longer projects tend to see a higher turnover of personnel and a greater likelihood of a change in objectives. “A reasonable recommendation would be to try to complete a project within 18 months,” says Alexander Budzier of Oxford university’s Saïd Business School. The state of South Australia recently proposed only commissioning IT projects lasting less than 90 days. Yet Mr Budzier adds that there is no statistical correlation between the value of an IT project and its success.
Longer projects tend to see a higher turnover of personnel and a greater likelihood of a change in objectives. “A reasonable recommendation would be to try to complete a project within 18 months,” says Alexander Budzier of Oxford university’s Saïd Business School. The state of South Australia recently proposed only commissioning IT projects lasting less than 90 days. Yet Mr Budzier adds that there is no statistical correlation between the value of an IT project and its success.
Everyone loves
‘agile’
Up to four-fifths of new IT projects are now implemented using agile methods, whereby pieces of the project are implemented quickly then improved if necessary. This can, however, require more active management.
Up to four-fifths of new IT projects are now implemented using agile methods, whereby pieces of the project are implemented quickly then improved if necessary. This can, however, require more active management.
Your project is not
different
“If the project manager thinks this is a unique project, then it’s going to explode,” says Mr Budzier. “And there’s a clear reason – they don’t benchmark themselves.”
“If the project manager thinks this is a unique project, then it’s going to explode,” says Mr Budzier. “And there’s a clear reason – they don’t benchmark themselves.”
Although much criticism has been
directed at civil servants, IT overruns are present in both the private and
public sector.
“The private sector is just much better
at hiding these things,” says Mr Budzier. He points out that large blue-chip
companies continue to operate failing IT systems because they are unwilling to
write down the expense.
Drawing on the work of Daniel Kahneman,
the Nobel Prize-winning behavioural economist, Prof Flyvbjerg and Mr Budzier
call for companies to forecast their costs better by comparing their projects
to previous experience.
The problems do not end with poor
forecasting. Organisations are often very ambitious in what they set out to
achieve – designing long projects that require customised software. That is
likely to be another mistake.
In a
report published this year, the Texas state
auditor’s office examined 13 IT projects, nine of which had overrun. It
concluded, admittedly on a small sample, that agencies using commercial
off-the-shelf technology “exceeded their budgets by a smaller amount and took
less time to complete their projects” than those that did not.
There is also an unwillingness to admit
to failings when they occur. In the US Air Force case, the can-do attitude of
some military officials meant concerns were not raised. “Program managers fear
that an honest delivery of program status will result in cancellation,” noted
an independent progress report into the project.
Poor communication – particularly
between business and technical experts – is a constant problem. “Corporations
are organised in hierarchies, in line roles,” says Mr Dreischmeier. “Doing
projects is different. Projects go across silos.”
Boston Consulting Group argues that a
project must have clear objectives, an understood business case, good
governance, clear deliverables and an agreement planning structure.
In recent years companies have laid the
blame for IT failures at the door of their contractors. The IT industry has
sought to borrow methods from the construction industry, where suppliers incur
penalties for late delivery. However, IT has special challenges.
“You’ve got lots of potential excuses
for things being not your problem,” says John Fotheringham, a partner at
Deloitte, the professional services firm. Suppliers can blame difficulties on
integration with existing IT systems. “They are very good at extracting extra
money,” he says. Clients can heighten this risk by changing a project’s
specifications after it has started.
Some suggest that more time should be
spent on the design of IT projects. “A transport project is often planned for
five years,” says Mr Budzier. “With IT there is very little upfront planning.”
Yet getting that right can also be
problematic. Unlike road technology, software changes very fast.
Boston Consulting Group’s Mr
Dreischmeier also warns that too much time can be spent on design. “I’ve seen a
project implementing a global finance system, and you’re just doing design work
for six months,” he says. “Then, when you put it together, it doesn’t work.”
An emphasis is now being placed on
“agile” methods, whereby work is broken up into small chunks and the design is
not considered complete before the work is started.
Those methods, which were used in the
Department for Work and Pensions’ benefits overhaul, have the advantage of
trial and error. Yet they also can require greater oversight.
Nonetheless, not everyone believes that
such soul-searching is helpful. “If reports keep focusing on failures, we risk
IT being seen as purely a cost and something that needs to be cut,” says
Georgina O’Toole, an analyst at TechMarketView.
The focus on budget and cost overruns
may obscure the wider benefits of a project. “You need a way to evaluate
whether your overall objectives have been met,” says Larry Maccherone of Rally
Software.
Some observers suggest that cloud
computing, which requires less on-site hardware, will simplify future projects,
rendering failure less common. Executives are also more technologically literate
now, and increasingly aware of the history of failure. “There are certain
changes that make me fairly optimistic that some things will be better,” says
Mr Dreischmeier.
For the moment, however, that is hope
over experience.
No comments:
Post a Comment